Quathiaski Cove Sewer Extension Project

Follow postings to this project webpage for ongoing construction updates. 

On October 3, 2016 the Strathcona Regional District received a grant from the Federal Clean Water and Wastewater Fund that has enabled the Quathiaski Cove Sewer Extension Project to be completed, while keeping the landowner contributions to a maximum of $9,100 per property. 

Construction for the Quathiaski Cove Sewer Extension Project is well underway.  Berry & Vale, the project contractor, broke ground in April 2017 and is on schedule to complete the construction by the end of July.

This project is extending the existing sewer service infrastructure to include 43 properties in the Quathiaski Cove area.

To learn more about the project, please review information from a recent info session here as well as the Project FAQs

For enquiries, please contact the SRD office at 250.830.6700 or engineering@strathconard.ca.

Koers and Associates Engineering Ltd. will oversee the project, starting with the re-tendering process. Progress made will be reflected in schedule updates below.

Project Schedule

Current Stage Time Frame  Project Milestones
  COMPLETE Tender process
    Awarding the tender
  COMPLETE Tender agreement
    Construction period
Week of April 3, 2017 Construction begins
  July  2017 Construction complete
 
 
    Connection Period
  Tentatively November 2018

Deadline for connecting to

the extended service